MPCB orders Adani firm to halt work on labour camp at Satara pumped storage project


The Maharashtra Pollution Control Board (MPCB) has directed Adani Renewable Energy One Ltd to immediately stop excavation and construction activities at a temporary labour camp site in Satara district after finding that work had allegedly begun without the necessary environmental clearance and permissions.

The labour camp, located in Sawargahar village in Patan taluka, approximately 300 kilometres from Mumbai, is associated with the company’s proposed 1,500 MW Tarali Pumped Storage Project.

In a stop-work notice issued on November 20, the pollution control board stated that the company had commenced excavation and development activities at Gat Nos. 33 and 34 in Sawargahar village for setting up a temporary labour camp and carrying out storage-related activities without informing the regulatory authority or obtaining the requisite permissions.

The board also observed that the company had not secured environmental clearance from the competent authority for the excavation and development work.

𝐒𝐭𝐨𝐩-𝐰𝐨𝐫𝐤 𝐨𝐫𝐝𝐞𝐫 𝐢𝐬𝐬𝐮𝐞𝐝

The notice was issued under Section 33A of the Water (Prevention and Control of Pollution) Act, 1974, and Section 31A of the Air (Prevention and Control of Pollution) Act, 1981.

Invoking these statutory provisions, the MPCB directed the company to immediately discontinue all ongoing and proposed excavation and construction activities at the identified site.

The order also prohibited the company from resuming any development work without obtaining prior permission from the pollution control board.

The regulatory authority warned that failure to comply with its directions would invite legal action under the applicable environmental laws.

𝐈𝐧𝐬𝐩𝐞𝐜𝐭𝐢𝐨𝐧 𝐟𝐥𝐚𝐠𝐬 𝐯𝐢𝐨𝐥𝐚𝐭𝐢𝐨𝐧𝐬

According to the notice, MPCB officials inspected the project site on November 20 and examined the excavation and development activities being undertaken there.

Following the inspection, the Satara sub-regional officer submitted a proposal recommending legal action against the company for the alleged violations.

The board subsequently issued the stop-work directions, citing the absence of necessary environmental approvals for the temporary camp and associated activities.

The MPCB noted that it had earlier granted the company consent to establish the 1,500 MW standalone pumped storage project in April 2025, subject to specified terms and conditions.

However, the existence of that consent did not remove the requirement to obtain applicable permissions for the excavation and development activities identified in the notice.

𝐏𝐫𝐨𝐣𝐞𝐜𝐭 𝐥𝐢𝐧𝐤𝐞𝐝 𝐭𝐨 𝐞𝐧𝐞𝐫𝐠𝐲 𝐬𝐭𝐨𝐫𝐚𝐠𝐞

The Tarali Pumped Storage Project is designed to provide electricity storage capacity through a system that uses water reservoirs at different elevations.

Such projects typically store energy by pumping water to a higher reservoir when electricity is available and releasing it through turbines to generate power when demand rises.

The 1,500 MW project forms part of efforts to develop energy storage infrastructure capable of supporting the integration of renewable power into the electricity grid.

The MPCB’s latest action specifically concerns excavation and construction activities for the temporary labour camp and related storage facilities at the identified location.

The company will be required to secure the necessary permissions before restarting the activities covered by the stop-work notice.

The notice did not specify whether the directions would affect the broader construction schedule of the pumped storage project.

Latest Posts

Don't Miss

Massive Turnout Marks BJP Nomination Rally in Assam; Deputy CM Arun Sao Leads Campaign Push

Dhemaji/Lakhimpur, Assam: Arun Sao, Deputy Chief Minister of Chhattisgarh, joined

Japan PM Takaichi Skips Controversial Yasukuni Shrine Visit on WWII Surrender Anniversary

Prime Minister Sanae Takaichi avoided a visit to the controversial

Indian Railways Approves ₹976 Crore Multitracking Project Between Danapur and Fatuha to Boost Rail Capacity in Bihar

New Delhi / In a major infrastructure push for Bihar’s

UWB tracking: Soon, technology behind AirTag could do more than find lost things | Tech News

Ultra-wideband (UWB) is usually mentioned alongside location trackers, digital car